7/30/21 – BRP
Well……… it has been a challenging past 2 weeks. We received 4”
rain in 72 hours 7/22-7/25. This set us back a few days. We’ve been able to get
back on track a little this week. Landscapes Unlimited is committed to
still making the significant completion date Sept 3rd. They have
added several more employees and will bring more in if necessary to make the
completion date yet. We completed hole
#1 on 7/27 and have completed portions of #8 and #18 as of today. We hope to
finish 8,9, and 18 by the end of next week. Which will give us 11 complete
holes through sod. That will give us 7 holes to complete in 4 weeks which
should be attainable, weather permitting. #10, and #11, and #12 are currently
being shaped. On a bright note...not a single new complete bunker washed out during the storms. This was a major test for the new bunkers and the drainage and they performed very well.
G&G completed all aerification of fairways, roughs, approaches,
and tees the week of 7/19 just in time for the rain. We spent another few days cleaning
the golf course up again this week. We have begun dethatching the tees,
approaches, and fairways this week. Due to storm clean up we were not able to
finish, but hope to finish next week. G&G continues to top-dress the sod
around the new bunkers in order to mend the new sod to the existing turf. We’ve
used about 500 tons of sand so far to top-dress sod. G&G will continue the
desert vegetation next week. We are currently working on the #16th tee. The storms have
definitely put a large dent into our in-house projects. The desert area on #5
tee is still drying out and we will fix up the area once we can get equipment
in. Once again, the drainage retention work that was completed in 2016 on #4,5,7 worked perfectly as containing
the damage of 4” of rain coming off Pinnacle Peak Road.
|
Aerifying Fairways |
|
Aerifying Fairways |
|
Dethatching - Verticutting Fairways |
|
Topdressing Fairways #2 |
|
Landscaping #16 Tee - Drip Irrigation and Holes Dug, Ready for Plants |
|
Wash/Retention between #4 & #7 - Very Full After A 2" Downpour |
|
Front Greenside #6 Immedietely After A 2" Down Pour, Standing Water In The Approach But No Wash Out or Standing Water In The New Bunker |
|
Water Pouring In From Pinnacle Peak Rd. |
|
#5 Tee Retention Holding Water |
|
#18 Rough Shaped Areas Holding Water Because No Drainage Is Installed Yet. |
|
Installing Exit Drainage #1 Front Bunker |
|
Installing Capillary Concrete #1 - 2nd Right Fairway Bunker |
|
Rough Shaping Practice Bunkers |
|
Practice Bunker Shaped |
|
Practice Bunker Ready for Drainage & Sod |
|
Front Right Bunker #8 - Added Back In By Andy Staples |
|
Front Right #8 Completed. |
|
Left Green side Bunker Interior Drainage Being Installed
|
|
Left Greenside #8 Being Sodded |
|
#9 View From The Tee With New Shaped Bunkers |
|
Left Bunkers #10 Being Shaped |
|
#10 Left Bunkers Shaped & Irrigation Being Re-Installed on the Right |
|
#10 Right Greenside Moved Back and Expanded Approached Right Of Greens & Irrigation Being Re-Installed |
|
#11 Tee Expanded and Tied Into The Back of #10 Greens. #11 Green, White, Blue, and Black Tee Will All Be Combined To Create Multiple Yardage Options. |