We hope everyone is doing well!!! We are in the final
stretch of the spring tournaments and events. The Sunrise, Salida, and Sunset
were great events. We hope everyone and their guests had a great time. In a
couple more weeks the heat will be arriving, and the end of the winter season
will be here.
The course did well throughout the entire winter season. We
were very happy with the turf conditions. The Greens have maintained a 12-13
readying on the stimp for the entire season. The new collars are thriving and
performing well. The overseed withstood the cold snaps of winter and we are
seeing a healthy amount of Bermuda grass emerging already.
You will see over the next several weeks that we will be
verticutting the greens. The verticut will be visible but will not affect the
playability. We will be performing a light verticutting, brush, and grooming
through the spring to help remove old leaf tissue and make room for new
emerging tissue. These processes also help to increase plant health and
readiness for the stresses of summer.
As mentioned before, we are seeing a tremendous amount of
Bermuda grass coming through the overseed. This is a great sign for transition.
Additionally, we will be applying the 1st application of 2
applications of a herbicide in mid-April and begin slowly removing the
ryegrass. The 2nd application will be applied the 2nd
week of May. This herbicide will begin the 10–12-week process of slowly
removing the ryegrass and allow the Bermuda grass to outcompete the ryegrass.
The effects will not be sudden or immediate and will not disrupt play. The only
indication will be the ryegrass will be slightly lighter for about a week. This
is the same process we have been using for several years now and has proven to
be very successful at transitioning the Bermuda grass back.
Green and Grounds have begun to add more vegetation to the
deserts. Several areas were not completed when the project began during the
Bunker Renovation Project. We recently completed the area by #7 bathroom, #2
tee box, and #17 green. We have several sporadic areas 10-17 that we will be
finishing up through the summer.
Progress continues on the Golf Course Maintenance Facilities.
The demolition has been completed and
signed off by the City of Scottsdale. The footers for the foundation have been
dug and partially framed. However, several unexpected challenges have arisen
including;
- Engineered plans had to be re-engineered to
secure two foundations together, as the existing foundation was different than
expected.
- The water source line for the bathroom on #7 had
to be relocated.
- The septic line from the bathroom was found to
have several issues causing the need for replacement.
- The City of Scottsdale required our permit to be
changed from a renovation to a new build.
These items are being worked on but are currently delaying
the footers and foundation pour.
Despite all the challenges the General Contractor is still
optimistic about finishing the building by July.
In addition to the new building, several other items are
being remodeled and/or improved. Upon completion of the new building, the
entire yard and existing structures will all be updated to match. The following
is a list of the other areas in addition to the new building.
Important to note that the additional projects below were
included in our estimated budget approved by the membership.
- A large room was segmented last fall into 3
smaller rooms. The new storage area allowed us to relocate from the old
building the chemical/fertilizer storage, operation supplies storage, and the
irrigation parts room. By moving these storage areas out of the old building we
were able to expand the future lunchroom for the staff.
- Another large room was segmented into 2 separate
rooms. These 2 new rooms allowed us to relocate the mechanical parts storage into
a new climate-controlled room. The other room is our temporary lunchroom for
the staff until the new building is completed. Upon completion, the room will
be converted into a small power tools storage area.
- The rear gate and wall were moved late last
summer to allow us to expand the building.
- A new gas tank is also required. The life
expectancy of the fuel tank is 25-30 years. Our current fuel tank is 25 years
old. The fuel is being relocated to a more convenient area in the middle of the
yard for better accessibility. Instead of moving the old tank and having to
replace it again in a few years, it was decided to purchase a new tank for the
new location.
- The west side of our yard is currently a dirt
yard. We will be paving this area with asphalt. The new area is approximately
13,000 sq. feet.
- A 20ft x 80ft shade structure will be installed along
the west wall to protect our large specialty equipment from the sun.
- The remaining portion of the building will also
be refurbished. The roof will be resealed/repaired, and all walls will be
repainted.
- In the mechanics bay a small new room will be
constructed with ventilation to enclose the reel grinders. This will help
shield the noise and help control the particulate matter from sharpening out
mower reels. Additionally, a small wall will be constructed to enclose the
large air compressor to help with the noise.
- A new water line from the meter by #17 green to
the shop will also have to be installed. A portion of the line was trenched
from the meter to the parking lot. The remaining line will be trenched and
installed later.
G&G has been aiding the contractor with several of the
trenching projects to help keep the costs down. This requires removing labor
from the golf course during these special projects. Additionally, the operation
of G&G has been impacted significantly by the demolition and construction.
We continue to ask for your patience and understanding as we work through this
large project.
We look forward to finishing out the season. We wish
everyone a safe and fun summer wherever you may be.
Regards,
Cody Horstman, Director of Agronomy
|
New electrical service for fans installed for #4,#5,#6 |
|
New vegetation and planings on #7 bathroom |
|
New vegetation #7 bathroom |
|
Vegetation #7 Bathroom |
|
Our new tri-plexes(2) have finally arrived that were ordered 2.5 years ago |
|
Our Mobile Mini Office
|
|
Office for the G&G operations and our central irrigation control |
|
Digging up the central irrigation communication lines to move to the mobile mini office |
|
Splicing irrigation communication wires and finding a surprise water line. |
|
Toro Irrigation Technicians helping move and install the hardware for the central irrigation controls into the mobile mini office. |
|
Demolition of the old showers in the locker rooms. |
|
Found a snake den under the old showers during demolition |
|
Start of demolition |
|
Foundation and Footer demolition.
|
|
Demolition complete. The existing/remaining building to the left. |
|
Framing new footers
|
|
Framing being completed for foundations poor |
|
Building Sewer / Drain lines roughed in and ready for city inspection.
|
|
Digging in the new sewer line from #7 Bathroom to the septic tank in the west yard.
|